Latest News

Published On: January 15th, 2016

1.15-1

Wausau, WIS-

The cold this week didn't slow down progress on Phase II of the Athletic Park renovation. Work continued inside of a tented and heated area over the new concession stand and group outing area. The project is on schedule to be finished by the start of the 2016 Woodchucks season. 

Highlights from the week of January 11-15 include:

-Exterior block work on the concession stand 
-Exterior block work on the new group outing area
-Installation of the outing area bar
-Application of a concrete top for the outing area

Next week we look forward to:

-Work being started on the outing area roof
-Internal work in the kitchen areas